Hello Friends,
Just to ask what does 'Budget supplement in Project' suggests in logs of change document in status management, Does it has any direct correlation with AVAC control on our budget.
The case is, I found -ve values against one WBS, and there is no inconsistency in the actual-commitment values. No one has deactivated AVAC , I check CE type etc. but I am still finding the reason that why system did not checked tolerance of budget against this WBS.
The change logs in the screen shot points on statement 'Budget supplement in Project' 'Inactive' . Can someone help me to understand what exactly it mean, can there be a case where by changing supplement values, I get -ve values in available budget count of WBS?
Kindly share your views on it.
Thanks in advance.
Regards
Saurabh