Hi Ganesh,
Forget all the things I have mentioned above..
So basically, this is a NEW SCENARIO..
So, I have two (2) chains: MAIN_PC and SUB_PC..
MAIN_PC - executed daily every 3AM
SUB_PC - executed daily every 8AM
This is the diagram of my SUB_PC chain which starts every 8AM daily:
START
|
INTERRUPT (based on after event of MAIN_PC)
|
ABAP PROGRAM (to send report)
What I want to do is to trigger the ABAP PROGRAM in SUB_PC if and only if the MAIN_PC was executed successfully..
Will the INTERRUPT process work before the ABAP PROGRAM in the SUB_PC chain if I made it AFTER EVENT?
Thank you!
Loed